MINUTES
OF THE WASTE WATER
COMPREHENSIVE LAND USE ADVISORY COMMITTEE
April 14, 2003
Meeting was called to order at 9:30 a.m. at the Kabetogama Fire Station.
Present were; Jack McMahon, Caroline Littwiller, John Stiegmeir, Ron Moyer
and Larry Warrington.
Jack asked that we meet early to discuss the conference call with Bridget
Chard and University of Minnesotas Engineering Team. A conference
call was asked for by Bridget to help everyone involved with the project
to be in agreement as to how to proceed. We need to set up a contact person
for Bridget in Kabetogama and supply her with information on the comprehensive
land use plan.
The conference call took place at 10:30 a.m. The University of Minnesota
Team needed information also about where and when the project would begin
and to what extent it would cover. All parties agreed to slow the pace
of the project so as to not get ahead of themselves and make unnecessary
moves.
Community education is the first place we need to begin. A tentative date
of June 22, 2003 was set to allow the U of M Team to set up informational
material about the project so everyone could become more familiar.
Following the June date, a community meeting would be set for July 7 and
8, 2003. July 7 there will be two sessions, one at 9:00 a.m. and one at
6:00 p.m. U of M Team will be there to inform and field questions from
the community. The July 8 session will be held from 9:00 a.m. until noon.
A mailing will be sent to all residents with the above dates and other
advertising will follow. Another session will be held at the September
3 meeting of the Lake Association to inform any resort owners who might
not be able to attend the two July sessions.
Budget and contracts were discussed and a plan for payment will be drafted
by the University and Bridget.
The call was ended at 11:30 a.m. The meeting was adjourned at 11:45 a.m.
These minutes are subject to approval at the next meeting of the committee.
Respectfully submitted;
Larry Warrington
<<<
Back
|